The insulation from PD was done yesterday. It was mainly on the external walls and the roof insulation will be done at a later stage.
The work on external wall insulation was not completely finished because the back wall on the upper floor has not been fitted with infill, or even the sisillation yet. Had been chasing SS on this to be installed quickly because we don't want the batts to get wet, and his answer was "will be this few days". Not happy.
The installers had made a mistake yesterday, they've used external wall insulation instead of the soundscreen on one of the corner which has pipe in it. Has raised this to SS, so hopefully they can change this before the plasterer work on this area.
Also, had found quite a few areas that the installer did not cut the hole properly for the electric sockets. Not sure will this cause any fire hazzards. Anyone has any idea?
The brickies had finished on the balcony yesterday, and they are working on the garage today.
Also, the carpenter came to fix some issues as well as install the front entrance doors, with locks. So we're now in Lock Up Stage, and had received call from CS today saying Bill #3 from PD is on its way. However, we don't intend to release the money until the back wall is completed. :P